Appendix I (2018) / Appendix H (2025) — freely discharging box gutters and the three outlet arrangements
Project record Step 3 — site data
Design process
Applied where the Standard adopts a standard size rather than the graph reading.
1
Design ARI
Determine the design ARI from Clause 3.3.4 (Table 3.3.4). The flow chart assumes
100 years for Australia and 50 years for New Zealand — if other ARI are selected, adjust the
flow chart to suit. The Appendix I design graphs are plotted for a 100 year ARI, 5 min
duration rainfall intensity.
2
Rainfall intensity for the site
Determine the rainfall intensity for the site from Clause 3.3.5.
(For guidelines, see Appendix D.) Read it off the BOM IFD tool for the site coordinates.
Australian place names and coordinates from GeoNames (CC BY 4.0). The BOM IFD grid
is 0.025° (≈2.8 km), so the grid cell may differ slightly from the site.
3
Site data, dimensions and layout
Obtain dimensions and other relevant data from physical observations and measurements,
plans or both (see Paragraph J2 for the rainhead example, J3 for sump/side overflow,
J4 for sump/high-capacity overflow). Recorded in the project record above.
4
Position of box gutter, expansion joints and outlets
Select position of box gutter, expansion joint(s) and outlet(s) based on the
approximate maximum catchment from Figure I1 for 16 L/s flow and the site rainfall intensities.
5
Catchment area Ac
Determine catchment area (Ac) for each section of box gutter and each
outlet (see Clause 3.4).
6
Design flow Q, and total flow through the outlet
Determine the design flows (Q) from Figure I1 using the rainfall intensity and
Ac. Design each box gutter and device separately. Note 2: the total design flow
is the summation of the design flow for each box gutter and the section of roofing discharged
directly into the sump.
7
Decision — is the design flow > 16 L/s?
If yes on the first trial, Ac needs to be reduced: review the selections at
Step 4. An increase in the number of outlets may require sumps rather than rainheads. If still yes
on subsequent trials, the design is beyond the scope of the general method.
8
Sole width wbg and gradient
Determine sole width (wbg) and gradients of box gutter from Figure I1,
using the design flow.
9
Box gutter depth
Determine the actual minimum depth of the box gutter from Figure I1, using Q,
wbg and the gradient.
mm
10
Vertical downpipe and rainhead depth hr
Select a size of vertical downpipe and total depth of rainhead (hr) from
Figure I3.
11
Check hr against Figure I2 Note 1
Check if the total depth of rainhead (hr) needs to be adjusted as required
by Note 1 of Figure I2 — the Figure applies only where hr ≥ 1.25 De
or 1.25 Di.
12
Length of rainhead lr
Determine the length of rainhead (lr) from Figure I3.
Note 2: Figure I3 is for a gutter gradient of 1:200; for steeper gradients determine the
equivalent 1:200 depth from Figure I1 first.
13
Size of the rainhead
Determine the size of the rainhead from Figure I2, using hr and
lr. The width of the rainhead equals the width of the box gutter.
7
Sole width wbg and minimum gutter depth dbg
Determine sole width (wbg) and minimum depth of box gutter
(dbg) for free flow conditions from Figure I1, for the box gutter with the
maximum flow.
8
Decision — is the total design flow through the outlet > 16 L/s?
If yes, review the selections at Step 4. Possible measures include repositioning
outlets and expansion joints, increasing the number of outlets, or a combination of measures.
If still yes on subsequent trials, the design is beyond the scope of the general method.
9
Decision — are the gradients of the box gutters flatter than 1:200?
If yes, the design is beyond the scope of the general method — the
graphs chart only 1:40, 1:100, 1:150 and 1:200.
10
Downpipe and depth of sump hs
Select the downpipe from Figure I4 for the total design flow through the outlet,
then determine the depth of sump (hs).
11
Minimum distance between duct and sump sides ℓoc
Determine the minimum horizontal distance between the sides of the overflow channel
and those of the sump (ℓoc) from Figure I6(a), for the largest flow in any one
box gutter.
12
Overflow channel width woc and depth doc
Select the width of the overflow channel (woc) and determine the minimum
depth of overflow channel (doc).
13
Height above the overflow weir crest ht
Determine the minimum height of the top of the box gutters above the crest of the
overflow channel weir: ht = [ℓoc + (doc + 30)] −
(0.7ℓoc).
14
Decision — is the minimum depth of the box gutter ℓoc +
(doc + 30) appropriate?
If no, review the selection of overflow channel width woc at Step 12,
or the selection of box gutter width wbg at Step 7.
mm
15
Size of the sump/side overflow device
Determine the size of the sump/side overflow device and sump from Figure I6, using
ℓoc, doc and hs. Sump length
woc + 2ℓoc, minimum 400 mm.
7
Sole width wbg and maximum gutter depth ha
Determine sole width (wbg) and maximum depth of box gutter
(ha) for free flow conditions from Figure I1, for the box gutter with the
maximum flow.
8
Decision — is the total design flow through the outlet > 16 L/s?
If yes, review the selections at Step 4 — reposition outlets and expansion
joints, increase the number of outlets, or a combination. If still yes on subsequent trials, the
design is beyond the scope of the general method.
9
Decision — are the gradients of the box gutters flatter than 1:200?
If yes, the design is beyond the scope of the general method.
10
Downpipe and depth of sump hs
Select the downpipe from Figure I4 for the total design flow through the outlet,
then determine the depth of sump (hs), which shall be not less than 150 mm
(see Clause 3.7.4).
11
Height of the overflow weirs ℓoc
Determine the height of the overflow weirs (ℓoc) above the sole of
the box gutter from Figure I6(a), for the largest flow in any one box gutter.
12
Height of box gutter above the weirs ht
Determine the minimum height of the box gutter above the top of the overflow weirs
(ht) from Figure I8, for the largest flow in any one box gutter. (The flow chart prints
“Figure I6(a)” here, but I6 is the side-overflow graph — I8 is the design graph
for the sump/high-capacity overflow device, and reproduces Appendix J Example 3.)
13
Decision — is ha < (ht + ℓoc)?
If yes, the minimum depth of box gutter dbg = (ht +
ℓoc). If no, dbg = ha.
14
Minimum depth of the box gutter dbg
mm
15
Decision — is ℓoc > 60?
This sets the datum level for the depth of the sump.
16
Datum level for the depth of the sump
If ℓoc > 60, the datum is the sole of the box gutter. Otherwise the
datum is the downstream sole of the overflow channel, (60 − ℓoc) below the
sole of the box gutter.
17
Size of the sump/high-capacity overflow device
Determine the size of the sump/high overflow device and sump from Figure I7, using
the required datum level, ha and ℓoc. The depth of the sump shall be
not less than 150 mm.
Design summary
Compliance basis: freeboard hf = 30 mm (Clause 3.7.2 / Figure I5);
gradients limited to 1:40–1:200 and rainhead design flow to 16 L/s (Clause 3.7.3);
downpipes at least Ø90 or 100 × 50 (Clause 3.7.8); box gutter systems shall
incorporate overflow devices (Clause 3.7.1).
Outlet arrangement
Validation — Appendix J worked examples
Digitised from the vector geometry of the Standard's own Figures I1, I3, I4, I6 and I8.
Standard detail
3D model
The solid is built from the dimensions calculated on this page, not from a fixed
model — change an input and it rebuilds. Drag to orbit, wheel to zoom,
shift-drag or right-drag to pan.
Rendered with three.js (MIT) bundled into this file, so it works offline.